This document relates to 2025-03, the Eclipse Foundation's multi-project Simultaneous Release of March 2025.
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan Information that stays the same for each release, like requirements for participation, communication channels, etc.
| Release | Date | Span | Due dates | Notes |
|---|---|---|---|---|
| 2025-03 M1 | Friday, January 10, 2025 | 01/03 to 01/10 |
|
4 weeks from 2024-12 GA |
| 2025-03 M2 | Friday, January 31, 2025 | 01/24 to 01/31 | 3 weeks from M1 | |
| 2025-03 M3 | Friday, February 21, 2025 | 02/14 to 02/21 |
|
3 weeks from M2 |
| 2025-03 RC1 | Friday, February 28, 2025 | 02/21 to 02/28 |
|
1 week from M3 |
| 2025-03 RC2 | Friday, March 7, 2025 | 02/28 to 03/07 | 1 week from RC1 | |
| Quiet period | 03/07 to 03/11 | No builds. It is assumed all code is done by end of RC2. | ||
| 2025-03 GA | Wednesday, March 12, 2025 |
|
5 days from RC2 |